On 15 September 2026, the Regional Court in Poznań awarded our client a total of more than PLN 300,000 in contractual penalties, default interest and litigation costs.
As part of an investment project involving the development of a logistics centre, our client had entered into a design-and-build contract with a contractor. The contractor was responsible for preparing the design documentation, obtaining a building permit, and constructing and handing over an office building with a hall for use. The value of the investment exceeded PLN 1,500,000.
The contractor failed to fulfil its contractual obligations. It neither prepared a proper and complete construction design capable of supporting an application for a building permit nor obtained the required third-party approvals, in particular from Poland’s General Directorate for National Roads and Motorways (GDDKiA). Our client therefore withdrew from the contract and charged the maximum contractual penalties provided for under its terms.
As the contractor did not pay the contractual penalties voluntarily, lawyers from the litigation department of Babiaczyk Skrocki i Wspólnicy prepared and filed a claim for payment on our client’s behalf. In its defence, the contractor relied on the excessive length of the administrative proceedings and alleged irregularities on the part of the building control authorities. The Court nevertheless accepted our client’s position and upheld the claim in full in the judgment referred to above.